Public Questions & Answers - 11.19.2004

Public Questions about the Possible Port Acquisition of the Georgia Pacific Site

November 18, 2004

On November 16, the Port of Bellingham hosted a public meeting to provide information about the Port’s due diligence study of whether the Port should acquire the Georgia Pacific property. The Port presentation was followed by public testimony. Some of that testimony included questions, which we have answered below.

If you have additional questions or comments, please email the Port at

Question: Is the RG Haley site in the deal? Is the cogen plant in the deal?

Answer: Neither the “RG Hawley” or the “EnCo-gen” sites are owned by Georgia Pacific and thus are not being considered for acquisition by the Port. If the current property owners are interested in selling these properties in the future, the Port would certainly be interested to learn the particulars to see if makes economic sense and be in the community’s best interest to incorporate those properties into an overall plan. The Port has been in discussions with Puget Power to better understand their long-term plans.

Question: What is the role of the City and how do they pay?

Answer: If the Port goes forward with the Georgia Pacific acquisition, the expenditures for environmental cleanup appear to outweigh the expected future value of the property. Therefore, the Port recognized early on that if the community’s vision for reuse of this property were to be achieved; partnerships would be necessary.

Because the scope of this undertaking will require such a significant investment of time and resources, the Port has been working a number of potential partners, including the City of Bellingham, the Department of Ecology, the Department of Natural Resources, the U.S. Army Corps of Engineers, and the National Oceanic and Atmospheric Administration. These agency partners have committed to support the project in a variety of important ways, including significant financial assistance from the Department of Ecology for funding the environmental cleanup requirements.

We have asked the City to develop the public park and walkway systems and install necessary public streets and utilities. The Port would however donate to the City at no cost the land necessary for public streets, parks and walkways. The value of this land has been estimated at $14.7 million.

The Port has not calculated the costs to develop the streets and parks. However, we believe that the GP site development, through payment of property and other city taxes, will be sufficient to cover the cost of construction. The infrastructure is not anticipated to be installed at one time. Rather it would be installed in phases commensurate with the rate of development. There will also be the opportunity to secure federal or state urban development grants to the City.

Question: Is there only 12% public space?

Answer: As has been emphasized, there are no detailed park plans at this time. We do know however, that our economic models indicate that the Port can afford to gift only so much property to the City at no cost and have the project remain financially feasible. Percentages are misleading because they include the existing 36+ acres of GP ownership that are underwater. For example, 30 acres comprise the GP Water Treatment Lagoon, 6.5 acres is aquatic habitat, and 15 acres consists of the current G.P. warehouse and surrounding asphalt area, which provide truck maneuvering and a cap of the former city sanitary landfill area.

Out of the remaining 80 acres, we have estimated that over 15 acres would be public parks. That is approximately 20%, or 1 out of 5 acres. The acreage figure does not include connection trails and sidewalks. There will be a balance between the amount of land set aside for development and what will become park area. Both the City and Port will require land to be sold and developed so that the costs associated with environmental clean up and installation of infrastructure can be repaid.

Having additional public space may be a valid community goal for this area. The question is; “If it is desirable, can and how would the Community pay and maintain the additional property?

Question: Should the Port sell or lease property, what are the pros and cons?

Answer: Early on, it was felt that selling - rather than leasing - the land would be an important redevelopment factor. While Port tenants pay an equivalent State leasehold tax, (similar to property tax); leasing does have redevelopment implications. Traditional financing is usually easier with land ownership. Redevelopment generally occurs at a quicker pace with land ownership. Additional public taxes - such as Property excise taxes – would be generated with the reselling of land. Finally, monies generated by land sales would repay the environmental costs at a much quicker pace than rents generated over time with leasing of properties

Question: What was sampled on site? What else did you find? Were groundwater samples taken?

Answer: Extensive environmental sampling of soils, soil vapor, fill materials, groundwater, surface water, marine sediments, and additional biological assessments have been performed at various locations on Georgia-Pacific owned property and adjacent areas in Bellingham Bay. The Port reviewed the results of roughly 100 technical studies that were conducted by expert consultants for the Port, Georgia-Pacific, Department of Natural Resources, Department of Ecology and others, as part of the Bellingham Bay Demonstration Pilot. Since 1996, a multi-agency work group under the Demonstration Pilot has led a cooperative effort among public and private parties to perform these investigations, including approximately 1,000 environmental samples, at a cumulative cost of over $5 million. The reports include environmental investigations, engineering evaluations, feasibility studies, human health risk assessments, eco-toxicology assessments, environmental impact statements, and cost estimates for alternative cleanup proposals. In addition, 92 samples were taken during the due diligence period. Findings were consistent with what the Port anticipated for a heavy industrial site and they included areas with mercury, petroleum byproducts and other contaminants. Detailed information about the studies is available for inspection in a document room the Port has opened at 1801 Roeder Avenue. For an appointment to use this room and review study documents, please call Mary Matyas, Port Executive Secretary at 676-2500.

Question: What are the health risks from the mercury in Bellingham Bay?

The potential health impacts of mercury in the Bay have been extensively studied by the Department of Ecology and the Department of Health, in coordination with the local Whatcom County Health and Human Services. The Department of Ecology is responsible for performing the investigations and studies to determine the extent of mercury contamination in the Bay from historical releases from the Georgia-Pacific mill site, particularly in the late 1960’s. Those studies include human health risk assessments. They will also establish cleanup standards to protect human health and the environment.

Specific protection of public health in Whatcom County is the shared responsibility between the Washington State Department of Health and Whatcom County Health and Human Services. These agencies use strict standards to determine potential risks to human health associated with eating contaminated fish and shellfish from contaminated areas. The mercury contamination problems in Bellingham Bay are at very low concentrations in localized areas around Whatcom Waterway. Based on this information, and environmental data from fish and shellfish, these agencies have determined that fish advisories related to mercury are not warranted in Bellingham Bay.

Question: How much habitat is there?

Answer: The Georgia-Pacific property and adjacent areas in Bellingham Bay include many different types of habitat, much of which has been degraded during a long history of industrial use. Important habitat includes riparian zones, estuarine areas, shorelines, shallow subtidal areas, and the marine environment. Some areas have recovered through natural processes, others have been restored under the Bellingham Bay Demonstration Pilot. For example, a contaminated shoreline area of approximately 5 acres on the Whatcom Waterway, known as the Georgia-pacific Log Pond, was recently remediated and restored to highly functioning habitat. The project was performed by Georgia-Pacific under federal and state agency oversight and is now populated by various sea life and birds.

As part of the Port’s proposed cleanup of the waterfront, additional areas will be restored to support state-wide salmon recovery efforts. New nearshore habitat benches are proposed at a number of locations within the Whatcom Waterway and adjacent areas. These habitat benches provide essential salmon and herring habitat.

The proposed removal of approximately 350,000 cubic yards of contaminated sludges from the GP treatment lagoon or Aeration Stabilization Basin (ASB) will result in the restoration of 28 acres of restored aquatic habitat on the Bellingham waterfront.

Question: What happens if there is an earthquake?


Answer: Since the site is fill, stability is a concern as it is with many waterfront communities. New and retrofitted buildings will be designed by structural engineers in accordance with local building codes, which will address seismic conditions and requirements. The Port has a long history of constructing facilities on fill areas where best engineering practices are used, and it will continue to use the most up-to-date practices.

Much of the waterfront, including the land owned by GP, consists of fill material placed over tideland areas. If a heavy structure is improperly constructed on filled land it would inevitably settle over time. In the event of an earthquake, liquefaction may occur. In those instances, improperly constructed buildings may crack or even collapse.

Because much of the waterfront is on fill, the Port is very experienced with construction upon this type of material. Heavy buildings may require attaching structural components to bedrock. These could be pile-supported structures at a depth to as much as 70+ feet.

At Bellwether a new construction technique was utilized whereby tons of stone and gravel were installed and compacted in columns under the building pads. This construction method; developed by the Germans and perfected by the Japanese, has been found to be superior to the traditional pile method. However it can be used in only certain soil conditions.

Question: What happens if the Port doesn't proceed?

Answer: Georgia Pacific will likely pursue a clean up of the upland property to industrial standards and seek private purchasers who would consider acquiring it as industrially zoned property. The Port would still have to consider whether or not it would move forward with its pending condemnation action on the treatment lagoon to convert it to a marina.

Question: I heard that City Hall is sinking. Is this site sinking?

Answer: Most of the heavy brick buildings on the GP site have been around for the better part of seventy years, and they show no signs of unusual settlement as evidenced by little or no cracking in floors or walls. The buildings at the GP site are built on fill material and may need foundations that are built on pilings driven deep into the ground for support. New construction will use best engineering practices to protect against any long-term settlement.

Question: As a moorage customer at the Squalicum Harbor, I would like to know more about how the new proposed marina will be funded. Will my moorage fees go up as a result of either the cleanup or the development of the marina? If so, what percentage above what I already pay can I expect? If not, what is the payment plan to fund the marina?

Answer: The Port has developed cost estimates for the cleanout of the ASB Lagoon, the construction of the new marina and the operation of the new marina along with maintaining and operating Squalicum and Blaine marinas. These cost estimates are based on completing the cleanout and construction of the first phase of the new marina by 2011 and the second phase by 2015 to meet expected market demand. There are two different rates that are calculated – one with receiving assistance from the Washington State Department of Ecology Toxic Waste Cleanup fund and one without.

The Port has a moorage rate charged to all customers of the Port’s marinas, the same in Blaine and in Squalicum. All customers pay for all costs associated with these two marinas, operation, maintenance and capital costs for expansion and replacement.

The Port has calculated moorage rates that would reflect these costs for the new marina using this same approach. The percentage difference shown is the difference between what the moorage customers would pay in 2020 without adding any new marina and adding the new marina with and without cleanup assistance.

The resulting, estimated, moorage rates are as follows:

2011 2020

No new marina – maintain Squalicum and Blaine $6.25 $9.07

Construct new marina – receive cleanout grants $6.25 $9.65

Construct new marina – receive no cleanout grants $6.48 $11.58

Question: I was interested in the "parking structures" referred to in the presentation. Where will they be located? I am particularly interested in the plan for a trolley up Pine Street from the waterfront to Western. Do you anticipate that the public will park their cars at WWU and take the trolley down to walk about the waterfront, or the other way around? In other words, do the plans include a parking structure to support WWU, or a parking structure at the Viking Union to support the waterfront project? Or both? If there are details on these parking structures, I would be interested in hearing them (# of spaces, projected cost, etc.).

Answer: At this time, the Port is in the due diligence phase to consider potential land acquisition. As such there has been no detailed transportation planning. That is expected to occur - should the transaction be completed - in 2005.

The Port hopes that parking lots can be provided in area-wide facilities rather than requiring the location of parking lots on the same lot as the development. We believe area-wide parking is much more efficient and we would hate to see large areas of the waterfront become parking lots, as is usually required by standard zoning requirements.

There would be sufficient parking within the area however to take care of the parking needs. In other words, we have not envisioned any parking facilities to be located off site and people transported to this location. We would hope that some parking garages could be located off of Chestnut Street so that both the existing downtown and newly developed areas could benefit from them.

The Waterfront Futures Group suggested the idea of a possible “skyway” or trolley up to Western Washington University. However, while a WWU presence on the GP site for some of its functions might be mutually beneficial, there has been nothing definitive. Therefore, the possible trolley is only an idea at this time. There has been little or no discussion of if such an idea is physically feasible, how it would affect the neighborhood or how it would be financed. That idea has to be more fully discussed - along with any transportation solution in 2005. It is our opinion, however, that a heavy emphasis in transportation routes will remain Chestnut/Roeder and Cornwall Avenue.


If you have additional questions or comments, please email the Port at






Subscribe to our Newsletter